GENEVA – Spring has brought renewal – and the restart of the City of Geneva’s West Main Street project.
At the March 23rd meeting of Geneva City Council, City Manager Joseph Varckette gave an update on the work, which has picked back up after the winter.
He said the contractor resumed work on such items as curb, sidewalks, drive aprons, etc.
“They started back today on some auxiliary items in and around the primary construction area on the west side of West Main Street,” he told council.
Varckette said the contractor was projecting a two- to three-week timeframe to complete these “non-road” items.
“Again, when we say two to three weeks, also this is dependent on the weather,” he added. “Of course, that’s subject to change.”
On Monday, March 30, cement was being poured along the street in the area of Rae-Ann Geneva Nursing and Rehabilitation.
Varckette, meanwhile, said the contractor was looking to re-start road construction in the first week of April.
“They’re still projecting to start around early April, which is what we always anticipated,” he commented.
He outlined the road work that will take place.
“For what they have to do, there’s an area between Lockwood and UH Hospital,” he told council. “If you’ve driven down there, you probably know it well. That was the area they were not able to get to before they had to shut the project down for winter.”
He said the contractor is estimating that there will be about a week and a half or so of work to do in that area for demo and construction.
“And then they anticipate another week and a half or so of paving for the full length of the project,” he added, stressing that all the timeframes are dependent on the weather.
“Keep in mind, that’s about it,” he said of the work he outlined.
Varckette also spoke about the closure that will take place in regard to the road work.
“When we get to the point of the closure during the road construction, again, we’re going to go back to the closure that we had previously,” he said. “And again, it’s a temporary closure that’s going to allow for one-way traffic westbound, of course in the north lane, for residential and business traffic only between Lockwood and West Street. East of Lockwood is going to maintain two-way traffic.”
Through-traffic will follow the posted detour around construction. He noted the detour will be well-posted.
He noted that the timing of the construction is tied to when the asphalt plant is open.