HARPERSFIELD TOWNSHIP – After more than five years, the Ashtabula County/City of Geneva Water Tower Project has begun.
Heavy equipment was at the site Monday as work began beside Route 534, near the Dollar General in Harpersfield Township.
According to engineer Joe Kordupel with Verdantas, the water tower will be built north of Dollar General, 300 feet from the road.
A drawing of the water tower shows that it will have the design of the Ashtabula County “A” with an inset of grapes, accompanied by the words “Ashtabula County, Ohio” and “Ohio Wine Country.”
Ashtabula County Commission President Casey Kozlowski was happy to see the project start.
“This water tower is a county project that we’ve been working on for well over five years,” he said. “It’s needed due to the significant growth and investment in the area and will support infrastructure needs well into the future. This project is both necessary and long overdue, and it’s an important step to ensure the long-term sustainability of our system and continued growth in the area.”
He noted that the “significant growth” in the area over the last 10 years has led to water pressure issues and other concerns, making the project both necessary and long overdue.
“There’s a number of things that it’s going to impact, specifically with customers, or residents, to the southwest of our water distribution system,” city manager Joseph Varckette said previously. “It would have a significant impact for them. It would have an impact on water pressure, fire suppression issues and also it would enable us to continue with the growth and development that we’re working so hard to achieve.”
According to Kozlowski, the project has a cost of $3.6 million.
“We received a $250,000 ARC grant to assist with costs along with a $2.4 federal allocation through Congressman Joyce’s Office which will assist with this project along with the South River Waterline Phase 2,” he said. “The share for Geneva will be 35 percent of the final calculated loan cost.”
He noted that the City of Geneva will share in the cost because its system will benefit greatly from the project.
The water tower project drew several comments online in the Geneva Facebook group on Jan. 24.
One person wrote, “Fabulous. Geneva is moving forward with the almost $4 million water tower project to be placed in front of Spire. This will make water available for Spire’s Clay Street apartment complex the area residents are opposed to.”
Kozlowski addressed the comment.
“This project is not related to the apartments,” he stressed. “The water tower has been in development for years. Our department has worked hard to secure grant funding to help offset costs, which has been one of the challenges in moving the project forward sooner.”
Great Lakes Crushing LTD of Willowick, Ohio, was awarded the bid for the project.
Construction is expected to finish up in November 2026.