PIERPONT TOWNSHIP – Apex Clean Energy has been hosting meetings in a number of townships in Ashtabula County that reside in the footprint of proposed project.
That project, dubbed Station Wind, would site 50-70 wind turbines within a footprint of eastern and south central Ashtabula County for a 300-megawatt wind farm.
Public Engagement Director Brian O’Shea, Station Wind lead Developer Rob Gee and Project Developer Liam Keough appeared at a public meeting of the Pierpont Township trustees on Wednesday, July 15, to answer questions and hear concerns about the project.
Apex Clean Energy, based in Charlottesville, Va., is looking to lease land totaling approximately 30,000 acres within a footprint of approximately 300,000 acres. The company is looking to lease property from private owners in Williamsfield, Wayne, Colebrook, New Lyme, Cherry Valley, Andover, Richmond, Dorset, Lenox, Morgan, Pierpont, Monroe, and Sheffield townships.
Turbine locations have not been selected, but they will be spread out over the entire target area. Approximately 12,000 acres have already been leased.
Prospective sites were chosen for the economical wind resource, existing transmission infrastructure and capacity and interested private landowners.
One of the first concerns to be raised at the Pierpont meeting was the issue of whether or not Apex Clean Energy can claim eminent domain over properties within the footprint of Station Wind.
“We do not have eminent domain,” Keough said. “It’s not a possibility. We cannot force somebody to host our facilities.”
There was a question as to how the energy would be transferred from the turbines to the FirstEnergy lines with some landowners signing leases and others not signing them.
“We need to establish land agreements with all of the landowners between us and the point of interconnection,” Gee said.
The questioner pressed, asking what happens if the agreements could not be secured.
“If we don’t get them, there’s no project,” Gee said. “There’s a lot of different scenarios that could lead to no project. Our inability to establish site control on all of the locations where we intend to place our facilities, that is one of the chief ways in which we kill the project because we need to establish site control everywhere we want to put something.”
Another concern that was raised was the proximity to Northeast Ohio Regional Airport where a turbine might be placed.
“I’m not exactly sure what the setback would be,” Gee said. “I think we’ve imposed a five-mile setback just to the area that we would consider leasing. Once we have more ideas about where we intend to place things, we will be doing outreach to the airport. We also are required to outreach to the FAA. The FAA has to weigh in on the suitability of every wind turbine site, or pretty much anything above 200 feet. The FAA has to determine that it is not a hazard to navigation in the airspace around it. In order to increase our probability of getting those types of approvals, we setback as far as we can from an existing airport.”
Another man asked why Apex chose the rural portions of Ashtabula County over siting the turbines on abandoned factory sites in Ashtabula.
“You’re suggesting putting it up where there’s most likely housing density or close proximity to the lake,” Keough said. “As we were explaining, or most projects these days, we’ll setback, in our case, five miles from the lake to avoid a few things – houses, but also birds. Birds tend to follow water bodies, as do most animals, and we like to minimize our impact to birds as much as possible. We’re federally regulated to do so, and that’s also regulated by the states.”
Gee expanded upon that explanation.
“Also, up along the lakeshore, too, are areas of much higher housing density and we have to take that into account for both sound and shadow flicker and maintaining those standards,” Gee said. “As far away as we can be from occupied dwellings gives us more optionality in siting things, but it’s also a recreational area and a place where people value the view shed. I understand people value the view shed in all kinds of areas, but along the lakeshore is one of those places we don’t want to disrupt tourism and we don’t want to anger those interests by trying to impose things there.”
O’Shea also said that if they chose abandoned factory sites in Ashtabula, there would only be space enough for a couple of turbines.
Concern was expressed about the loss of farmland within the county.
“Of that 30,000 acres (that we’re looking to lease), only about 150 acres will actually be used for this project,” Keough said. “You can farm right up to the edge (of the foundation of a turbine). It’s, in fact, very compatible with farming and that’s why farmers consider a very lucrative to not entirely replace their use of the property, but diversify. They can farm alongside turbines instead of turbines taking over their entire property.”
A man who moved to Ashtabula County in recent years expressed his concern that residents might lose some of the reasons they had for moving into the area in the first place.
“We moved out here five years ago from a less populated area,” the man said. “One of the things I noticed about Ashtabula County is there’s a lot of rural property to build nice homes. They enjoy the country. They enjoy five or 10 acres of property. A lot of people have horses. A lot of people have big gardens. I drive down a lot of rural roads. My wife and I go out a lot just to drive, and we really love this area. We feel like this is going to change the character of our area, which is depressing.”
That man wanted to see documentation from Apex stating that Ashtabula County is the best location for a wind farm.
“Ohio law requires that the Ohio Power Siting Board that a project represents the minimum adverse environmental impact after considering alternatives,” the man said. “My question, have you done the study and are you going to, or are you doing the study and are you going to release that to the people central and eastern Ashtabula to show us that you’ve looked at other sites for this project and that this site is, in fact, the best site, and that it is less harmful doing it here than in those other sites because required to do that before you get approved.”
Gee said the study has not been completed.
“Before we go on with this, I would like to see that you’re studying other locations before you ruin my back yard, that you find other places where there’s less density, less people that have come out here to enjoy nature, enjoy the country,” the man said.
Gee expressed his understanding and tried to explain why the study has not yet been completed.
“The reason we haven’t done the study yet is because we haven’t done any studies yet on our intended location, so we can’t do an alternatives analysis if we haven’t yet chosen the locations for our turbines,” Gee said.
The man pressed his point.
“You’re putting out $1.7 million in leases before doing the study,” the man said.
Gee tried to explain the process further.
“We’ve done desktop studies, but until we’ve leased the ground, we can’t walk the ground,” Gee said. “We can’t walk onto your property unless we have a land agreement with you to do so, which means we can’t have biologists out there, we can’t have surveyors out there.”
The man said he would like to see at least a preliminary study showing that there’s not less dense areas in terms of population.
A man said that the value of properties surrounding the turbines will decrease.
“If you look at places that have had wind projects, there’s not been a decrease of property values,” O’Shea claimed. “People continue to buy homes.”
Noise pollution was also a topic of discussion.
“I spend time in Delaware and in the town I live in, there’s a wind turbine,” a man said. “I have friends who live about a fourth of a mile from that turbine, and I’m going to tell you that the noise is significant, especially when it’s windy. The whirring sound and constant hum is noticeable.”
Another person asked what the decibel levels on the turbines were expected to be.
“Rob did a project in Maine, and they did a study right before the permit, they found that wind turbines do not produce sound above 42 decibels, DBA,” Keough said. “It takes into account pressure. That was equated to nothing louder than wind blowing through the trees with leaves.”
Gee also said that the noise a turbine emits is dependent upon when the turbine was built and what kind of turbine it is.
“There’s a lot of technology on modern turbines, which is the kind we’re talking about, that is intended to minimize the sound output,” Gee said. “There are also sound standards and sound measured from particular distances and where you can only cite turbines outside of particular distances from occupied dwellings, so we have to model what the sound output will be as received at each one of those dwellings. Every single place around the project area where sound can be received from a turbine or multiple turbines needs to be modeled and it needs to be below the OPSB sound standard. In Maine, that was 42 DBA, and so what Liam is saying is that roughly 45 DBA is the sound of the wind blowing through the trees.”
A person noted that somebody has a map of locations for all of the bald eagle nests in the county.
“You’re just going to chase them right out of the way,” the man said.
A woman said the bald eagles are just coming back.
“We have to set back a mile from a bald eagle’s nest,” Keough said. “That’s regulated by the state.”
Gee said that Apex is aware there are a number of areas within the proposed footprint of the project that are not suitable for siting a turbine.
“There’s a lot of things inside that outline that we know perfectly well are not appropriate areas for wind turbines, but that’s part of the work that we do in developing the project to determine with greater granularity where things can and cannot go,” Gee said. “That is the area of focus for our leasing efforts.”