PERRY – In a major policy shift, acting Perry Mayor Elias Coss announced Thursday, July 16, that the village will not offer a property tax abatement or a payment in lieu of taxes (PILOT) program to Province Group for its proposed artificial intelligence data center campus.
During the meeting, Coss said the administration formally communicated the decision to the California-based real estate developer.
Province Group had previously requested a 15-year, 75-percent tax exemption on improvements to the 217-acre former Champion Farms site.
Additionally, Coss said council plans to enact a one-year moratorium on future data center permits. The moratorium will exclude the pending Champion Farms development currently under contract.
These announcements follow months of opposition from residents.
Local advocacy groups have opposed the six-building, 1.2 million-square-foot project. Community members raised concerns regarding noise, environmental effects on water quality and a lack of transparency.
By denying the incentives, Perry Village leaves Province Group responsible for its full local property tax burden. This moves the village into alignment with surrounding communities, such as North Perry Village and Madison Township, that have recently implemented similar data center moratoria to grant time to reassess zoning codes.
During the meeting, council also reviewed several municipal projects.
Chief Fiscal Officer John Roskos noted the upcoming 2027 budget planning process is underway, requesting initial proposals from department heads.
Council also reviewed several key infrastructure projects, noting substantial progress alongside severe budgetary challenges caused by global supply chain disruptions.
Surface treatment, vibrant court coloring and structural net systems are fully scheduled for installation at the local pickleball court by late July. Current expenditures for the recreation project stand at $53,080, which aligns safely under the $55,000 maximum grant awarded by NatureWorks.
To protect this brand-new asset from vandalism and vehicle trespass, council voted to dedicate a $1,000 safety grant from the Public Entities Pool of Ohio (PEP) toward an entrance security gate from Shannon Fence, overriding previous proposals to use the funds for traffic cones and road flares.
Meanwhile, the drainage infrastructure at Thompson and Green Road is officially complete and passed its final walkthrough.
However, the accompanying roadwork hit a massive financial snag; due to inflation officials linked to the ongoing war with Iran, the competitive asphalt bidding came in $250,000 over budget.
Consequently, the council has delayed widening and repaving Green Road until 2027. The village plans to bundle the pavement project with northern Madison Township roads next March to secure better seasonal volume pricing from contractors.
Separate from the delayed paving, the Green Street waterline replacement project remains on track, shifting to a mid-August start date with a contract completion deadline in late October.
Newly appointed Police Chief Dan Shook delivered his department report, highlighting operational efficiencies and a transition toward community-oriented policing.
He praised Sgt. Orr for condensing the field training of a newly hired officer. Because the incoming officer possessed significant prior law enforcement experience, the shadowing phase was completed immediately, allowing him to be available for solo patrol shifts.
Coss noted that under Shook’s leadership, the department has successfully rebalanced its daily operations toward highly visible community engagement and stricter traffic safety.
This presence has run parallel to a sharp statistical shift in traffic enforcement. The ratio of citations to standard warnings has increased significantly, directly yielding a rise in OVI arrests and the discovery of active criminal warrants during routine, minor traffic stops.
Shook is currently completing a comprehensive strengths-and-weaknesses analysis of the entire department to present a formalized long-term improvement plan to the council.
Perry Village Council will meet next in regular session on Thursday, Aug. 13. Meetings are held at village hall and begin at 7 p.m.