JEFFERSON – A planned wind power generation project has been deemed unviable after most local townships voted to limit or ban utility-scale wind power facilities, according to a senior developer.
Robert Gee, senior development manager at Apex Clean Energy, said that while he couldn’t comment on the viability of a different wind power project, Station Wind has no viable path forward for development.
Apex Clean Energy, based in Charlottesville, Va., was in what it characterized as the early stages of developing Station Wind, a planned 300-megawatt wind power project using 50 to 70 wind turbines erected across much of the eastern portion of Ashtabula County.
The clean energy company was seeking to lease property from private owners in Williamsfield, Wayne, Colebrook, New Lyme, Cherry Valley, Andover, Richmond, Dorset, Lenox, Morgan, Pierpont, Monroe and Sheffield townships.
Casey Kozlowski, Ashtabula County commissioner, said he hadn’t heard anything official from Apex Clean Energy as of this publication’s print deadline, but that the commissioners were working on a map of where future wind power projects would be permitted after townships were allowed to hold a vote under SB 52.
Ohio Senate Bill 52 is a 2021 state law that significantly altered the approval process for utility-scale renewable energy developments by granting the county commissioners veto power over wind and solar projects. The law overrides the public utility exemption, giving the county authority to prohibit or limit the size of large wind and solar facilities.
Counties can proactively designate restricted areas where wind and solar developments are entirely banned or establish energy development districts where they are permitted.
Rather than make the decision from Jefferson, Kozlowski said the commissioners wanted to inform townships on what SB 52 calls for and get the trustees’ input before assembling a map for Ashtabula County.
SB 52 governs “economically significant” projects of between 5-50 megawatts and “utility scale” projects of 50 megawatts and over, giving local townships the option to decide whether the entire township is open for renewable energy development, part of it or to close it altogether. Projects of 5 megawatts or less are governed by local zoning codes.
The commissioners asked each township to identify areas where utility-scale projects should be restricted, if any, considering the needs of agriculture, economic development, residential areas, natural resources, local infrastructure and community identity, according to Kozlowski.
The townships had a 90-day review period, ending Sept. 1, to go over materials and confer with local officials before holding public hearings before passing a resolution and map with the rationale for restricting renewable energy development.
“At the county level, the process we undertook to regulate this, including input from each township, has been completed,” Kozlowski said. “We are now developing the mapmaking and public process, and we expect to act on a final map delineating the restrictions here soon.”