CONNEAUT – The members of the city council in Conneaut recently faced many questions as the debate over whether or not a data center should be allowed to be built in the city reached a fever pitch. Council members had plenty of their own questions, many of which they tried to answer through their own research.
With M2 Development Solutions in attendance for a city council work session on Monday, Oct. 5, many of those questions received long-awaited answers.
Questions the city council asked M2 Development Solutions owners Mark Schonberg and Mark Vogel included:
• Question: How many does a data center employ, depending on the size?
“Not very many,” Schonberg said. “Probably at 20 megawatts, you’re looking at about 20 full-time individuals. The salaries usually range, it’s different, but I’d say in a place like this, probably the entry salaries are around $100,000 and the high-level management are probably around $200,000. There’s a kind of a star by that because some customers who put their data in the data center, they want to have their own on-site representatives that I would not employ. As you scale, you don’t really get very many more jobs because the tasks don’t really increase that much.”
“Construction-wise, probably an average of about 200 workers,” Schonberg continued. “It will fluctuate. Sometimes you might have 500 and sometimes you might have 30. It’s kind of like a traditional construction project in that manner.”
• Question: In Ohio, where are your locations?
“Right now, the only acting site we have in Ohio is Conneaut,” Schonberg said. “We have another site that we’re looking at. It is in southeastern Ohio towards the West Virginia border. The only things we have in service right now are in Oklahoma.”
• Question: Could you guarantee no surcharge for electric or water usage?
“Yeah, if you just put that as part of our contract,” Schonberg said. “And, if there is a certain charge, we would have to pick up that difference.”
• Question: In the newspaper, Mr. Vogel, you said it would be a 500-megawatt facility and today I’m hearing something different, 20 to 200, could you speak on that a little bit?
“The study that we paid for from RH Gas was for a 500-megawatt maximum buildout,” Vogel said. “Let’s just say that we would set it up as a campus type of development. We wouldn’t have a million-square-foot building. We’d have 200,000-square-foot buildings or 250,000-square-foot buildings. But, yeah, if we had 500 megawatts over the next 10 years and we had a dozen 200,000-square-foot buildings, it would be like an office park, the way I would look at it. The more power you have, it really means the more money you can make.”
• Question: You also need power for redundancy, for maintenance, for power outages. What would be your plans for that?
“The natural gas system would be that, or we’d probably come up with some sort of storage to bridge it for three days, maybe, max,” Schonberg said. “The equipment doesn’t fail. What fails is the energy supply. What we would do is we would come up with a solution to store the gas that we needed on-site. We would store on-site probably 72 hours over capacity. We wouldn’t store extra gen sets if we could avoid it.”
“I think what you’re asking is, traditional backup generation is nasty, dirty diesel generators and you end up with 50 of them or 150 of them. We don’t want to do that. We want to have additional supply of energy, in this case, gas, on-site so we don’t have to have 150 diesel generators down there. That’s not going to make me happy and it’s not going to make any of you happy.”
• Question: You mentioned the location, and I wanted to understand, you said it was one mile away from something. What is it one mile away from?
“It’s a little less than one mile,” Schonberg said. “When we cite our power generation, we try to make it as far away as possible from the nearest people or housing developments.”
• Question: As far as water usage, are we looking at a closed-loop system?
“We’re looking at a closed loop system,” Schonberg said. “It’s kind of like a radiator system in the old house. The best way I can tell you is the new systems put in something that’s similar to anti-freeze, which makes (as far as the) heat transfer rate, [it] is very efficient.”
“There’s heat generated, but as far as water, typically, I don’t know if you have a golf course here, but normally golf courses use more water than the new designs (of data centers) use,” Schonberg said. “The old designs were horrendous. They had those open-air chillers and you just wasted tons of water. Even the turbines, the old turbines, are all water cooled. They would waste thousands of gallons of water an hour just keeping the turbines turning.”
• Question: The $10,000,000 question is, if the charter should pass and it is limiting a data center to 25, would you be able to move forward with your project?
“I would not even look at 25 megawatts,” Vogel said. “We have five or six other projects. First of all, you have to pay for all the land and there’s still a lot of projects out there. The key point is we will try to do everything that we can so that your worries aren’t there. I would not be purchasing a property if all we can do is 25 (megawatts), regardless of our project in Pennsylvania.”
Instead of asking a question, Ward 2 Councilman Chris Castrilla made a comment.
“Just so people know, I support a data center,” Castrilla said. “I went to Texas here a couple of months ago and went to right outside Waco. I was at a facility that was 85 to 100 megawatts. Couldn’t hear a damn thing. I went around the whole 500 acres, stopped at different locations. It was a new one. It was Google. I heard nothing.”
Ward 1 Councilman Rick Gaugh also commented.
“When I went to New Albany, they said that 50 percent of the bad press for it was from a foreign country,” Gaugh said. “I do believe it because what I saw and what they said I saw is altogether different. I’ve been in a data center, inside, and the chillers that were on the top of an apartment building in downtown Cleveland were just as noisy as the one over here and I could hear the noise from the air conditioning units. It’s a glycol system and one of our plants in town has the same system. It’s a cooling system. We don’t complain about that.”