CONNEAUT – After concerns were raised regarding the potential of a data center getting built in Conneaut, Conneaut City Council formed an ad hoc committee to consider zoning ordinances to protect the community.
The ad hoc committee, officially known as the Advanced Manufacturing Zoning Review Committee (AMZRC), hosted its first meeting on July 30 and, six weeks later, invited the public for an open forum at New Leaf Event Center on Tuesday, Oct. 13, to answer questions and address concerns.
“We were created by an ordinance passed by city council in response to the fact that our zoning code last received a major overhaul in the 1980s,” Committee Chairperson Jennifer Simpson said. “Clearly, the world of business these days is not the same as it was in the 1980s. Many, many things have changed, and so our city zoning ordinances need sprucing up.”
“What we’d really like to do is get ahead of the shift in manufacturing, especially the advanced manufacturing that’s happening, and make sure that our city ordinances are prepared to function in the world with advanced manufacturing,” Simpson continued.
Members of the committee include Simpson, Conneaut Health Commissioner Nichele Blood, Virginia Arp, Ron Williams, Lisa Specht, Angela Nelson and Kenna Coltman.
The AMZRC’s primary goal, as given by city council, is to draft an ordinance establishing a conditional-use permit framework for advanced manufacturing.
The committee, using a definition outlined by the City of Ontario, Ohio, which states that advanced manufacturing is “any manufacturing and assembly housed entirely within a building relating to the use or application of advanced manufacturing technologies, precision tooling, which includes 3-D printing; equipment and profit technologies; environmental and energy technologies; and information technology.”
Simpson stated that advanced manufacturing often requires a high level of unique skill training that is specific to each company and commonly involves computer technology, robots or other innovation to improve a product or process.
“In normal human being language, this is all the kind of industries that are really cutting edge and are technology heavy,” Simpson said.
Data centers are included under the umbrella of advanced manufacturing.
A conditional-use permit allows a home, business or industry to be built, under certain conditions, in a district zoned for something else. For example, a conditional-use permit allows a store to be built in a residential neighborhood.
“That also means that the conditional-use permit has to be approved on an individual basis by city council,” Simpson said. “It has to go to the Planning Commission. It might have to go to Zoning Board of Appeals.”
“An advanced manufacturer has to go through a process of special acceptance,” Simpson continued. “They have to go through a special process to be accepted to build there. That’s what we’re working on, is what goes on that list of things that goes on the conditional use program, where we say, ‘Okay, love to have you. Super excited. We need the tax base and the jobs, but here’s what we need from you.’”
The committee is targeting Feb. 8 as the date to deliver drafts of zoning ordinances to city council.
Once Simpson explained the committee’s responsibilities, the committee took questions from the audience including:
• Question: What can we, all of us here, do to help and support what you are doing?
“Educate people to what the purpose of the ad hoc committee is, because people think that we’re here to attract a data center,” Nelson said. “We’re here to set the ground rules, the guidance to protect our city. That’s what we’re here for. People aren’t paying attention to what we’re here for.”
• Q: What experience do committee members have regarding data centers?
“We all know how to do research, and it is very technical, if we don’t know the answer, we know where to go and get it,” Nelson said. “We’re going to get it from an expert. We are not experts. We don’t profess to be experts. We know to do the research. We know how to ask the right questions and find the right people if we don’t know the answers.”
• Q: If they’re given the green light, who monitors those processes to protect the water tables?
“Sampling would be done by (the city’s) wastewater department,” Blood said. “They would have would have to meet standards with Ohio EPA, as well, in order to keep their permit.”
• Q: Noise is a big concern for data centers, but that can be applied to all manufacturing. The neighbors are going to be awfully upset.
“We would mandate the decibels, the amount of noise that would be allowed,” Nelson said.
• Q: Are you looking at communities outside of Ohio for guidance in drafting the zoning regulations?
“We have, actually,” Specht said. “We’ve looked at some in Pennsylvania. There’s actually updated (information) with a lot of good suggestions that someone put together for everybody in Pennsylvania. We pulled a bunch of information from Loudon County, Virginia.”
• Q: Will there be more of these types of meetings as you progress?
“We’re still completely ironing out what the next day is going to look like,” Simpson said. “We know there’s going to be a second public meeting. We’re aiming for early January 2027 ahead of, hopefully, turning in our final report to the city. At that point, we’ll be farther along in the process of actually creating the sections of the conditional-use permit.”
“If you have a thought, question or concern, you do not have to wait until January,” Simpson continued. “Feel free to send it to us at any point.”
• Q: If the ballot referendum passes in November, does that eliminate the need for this committee?
“The referendum on the ballot is to limit the size of a data center that could come into Conneaut to 25 megawatts or less,” Coltman said. “It wouldn’t allow chaining additional data centers together, either, but that does not eliminate the need for what this committee is doing. We have to improve our zoning ordinances for any advanced manufacturing that can come into Conneaut, not just data centers. We’re looking beyond just the data centers.”
• Q: Will the cost of electricity rise with the amount that will be used by a data center?
“Right now, electricity is in such huge demand, and yes, data centers are the cause of that,” Nelson said. “However, as a mandate for the (conditional-use permit), we can have them bring their own power, and it’s called the behind-the-meter. Because we have this natural gas pipeline that’s come up through West Springfield (Pa.), to Conneaut to North Kingsville, and it’s going to be expanded, the power will be supplied by natural gas, so that takes the amount of electricity off the grid. It doesn’t compete with our electricity prices.”
• Q: What about the manufacturing in Conneaut already. Are you looking to fragment their businesses and drive them out of town?
“The businesses that exist in town are basically grandfathered in under the zoning that exists,” Simpson said. “There isn’t anything about these (zoning regulations) that should affect any existing businesses. Those businesses are already located in areas where they’re already properly zoned for the work that they’re doing. What we’re going to try and do is add that extra layer for these advanced manufacturing businesses that would not replace or go over top of the existing business and manufacturing.”
“It would be to guide putting those advanced manufacturing businesses someplace that is going to work for them, work for us, work for the community,” Simpson continued. “Certainly, we are not trying to interrupt any business that’s happening now. We’re not trying to decrease jobs or displace any of those businesses.”
• Q: When you submit your results to city council, what happens then?
“There’s a whole process by which any ordinance, whether it’s this one or anything else, gets made into an actual law for the city,” Simpson said. “It usually has to go through Planning Commission, it has to go to city council. They do their normal readings and revisions. They may send it back to planning commission. They could also reserve the right to reach out to the ad hoc committee for any information we still have. It would follow the normal process of any of the ordinances that are passed through the city.”
• Q: Do the people of Conneaut get to vote on the acceptance of this regulation?
“I don’t believe so, and we can follow up and find out for sure what that exact process is, but in my understanding, it would be treated like any other ordinance,” Simpson said. “The best way to get your feelings about this known is to contact your city council person or go to a city council meeting. The stuff that we’re working on, again, sunshine laws, it is accessible to people. When this gets drawn up, you can request a copy to look at, to peruse yourself. You’re allowed to make your own comments, but the process for actually getting it in law would be by city council voting yes or no on it.”
Questions, concerns and topics the committee can research should be sent to Nick Perkoski, the AMZRC’s city council liaison, at nick.perkoski@conneautoh.org. Committee meeting minutes and an FAQ can be found on the City of Conneaut’s website, conneautohio.gov, under the city council tab.